Sydney Metro Western Sydney Airport station site_St Marys

Sydney Metro

Home / Archive by category "Infrastructure"

The new Sydney Metro – Western Sydney Airport line is set to become the transport backbone of Greater Western Sydney. Spanning 23 kilometres, the line will connect the future Bradfield city centre in the south to St Marys in the north, delivering a fast and reliable link to the new Western Sydney International (Nancy-Bird Walton) Airport. 

MGP is proud to contribute to this city-shaping project. Our Hydraulics team are preparing workshop drawings for key stations along the route, including Bradfield Metro Station (formerly Aerotropolis), St Marys Station, and Airport Terminal Station. 

We’re delivering: 

  • Under-platform fire hydrant systems 
  • Stormwater and sewer design services 
  • Seismic restraints and bracketing across all systems 
  • All services in LOD400 to ensure high-level coordination and construction readiness 

This work highlights MGP’s role in supporting critical infrastructure for one of Sydney’s most significant transport projects. 

Aerotropolis Station, Airport Terminal Station, St Marys Station.

Client: Transport NSW 

Builder: Parklife Metro D&C 

Plumber: Doolan Co 

Plumber: Brownies Plumbing 

Sydney Metro Read More »

Wynyard Walk

Wynyard Walk

Wynyard Walk

The Wynyard Walk development provides full accessible pedestrian access between Wynyard Station and the new development at Barangaroo. It is expected to accommodate up to 23,000 office workers and up to 33,000 visitors per day. 

The project included a new western entrance to Wynyard Station, a new 3.5 metre by 9-metre wide underground pedestrian link, a new paved pedestrian plaza and pedestrian bridge with lifts and escalators connecting to the Barangaroo development.

MGP were awarded the design and deviation of water mains, sewer mains and storm water mains.

 

 

Client:
Transport NSW
Builder: CPB Contractors

Wynyard Walk Read More »

Pitt Street metro station

Pitt Street metro station

Pitt Street metro station

The development of Sydney’s CBD continues to provide the MGP Sydney Water team with interesting site specific challenges. These include dealing with heritage and oversized critical assets that require protection, whilst enabling new developments to be constructed and the CBD to grow.

MGP designed the Sydney Water infrastructure for the development of Pitt Street metro station.

The project involved a detailed major works design, building plan approval over/near heritage assets, tunnelling, deep basement excavations and anchoring.

Site challenges/solutions: Heritage assets surrounding the development needed to be protected from the construction works such as tunnelling, deep basement excavations and anchoring, our building plan approval assessment ensured all the supportive design documentation and correct construction approach was taken to ensure these risks were mitigated.

Additionally, the new Pitt Street Station will require construction work at each underground station entry, with the construction implemented in two (2) stages. MGP managed five (5) Development Applications with Sydney Water to attain the required certificates, approvals and protect the assets at each stage accordingly.

This in depth approval and connection schedule was implemented to ensure a successful delivery of the project.

Client:
NSW Government - Sydney Metro

Pitt Street metro station Read More »